Month: August 2026
Road works
Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure – at Charlbury, Fawler Road
A request has been received from SGN for a temporary road closure to apply to a section of Fawler Road, whilst essential gas main repair works are carried out.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 10 August 2026.
The estimated completion of the works is 13 September 2026, 24 hours daily.
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)





Road works
Temporary Traffic Regulation Order – S14 Road Traffic Regulation Act 1984
Temporary Road Closure – at North Leigh, New Yatt, New Yatt Road
A request has been received from Mott MacDonald for a temporary road closure to apply to a section of New Yatt Road, whilst essential rising main works are carried out.
A Temporary Traffic Regulation Order (TTRO) is being made to implement the temporary closure and will operate from 28 September 2026.
The estimated completion of the works is 23 October 2026, 24 hours per day.
(The maximum duration of a TTRO on a road is 18 months and on a footpath is 6 months, or until completion of the works, whichever is the earlier.)